Jasper has successfully completed and fully executed a LSTK EPC project in the Delaware basin for a repeat client. This is the third train Jasper has completed at this location. The client chose Jasper’s standard 200 MMSCFD Cryogenic Plant, along with a 290 GPM Amine Inlet Treater and 3800 BPD Single Tower Stabilizer, interconnecting piping, flare, utilities, instrumentation, electrical, MCC, foundations, and a fully automated Allen Bradley ControlLogix control system with Wonderware front end.
120 MMSCFD Cryogenic Gas Plant designed for rich Delaware Basin shale gas (6.0 gal/mscf), 90% ethane recovery, 99+% propane recovery, and includes: Product treating system, product pumps (1,300 psig discharge pressure), and 30,000 gallon product surge tank, modular MCC building, with 480 volt MCC and 4,160 volt soft starts for three 1,250 HP motors, 4,500 HP refrigeration system, I/A system, ethane rejection and recovery capability.
Job 387
60 MMSCFD Cryogenic Gas Plant
60 MMSCFD Cryogenic Gas Plant, Eddy County, NM, including inlet separator, slug catcher, and stabilization for 4,000 bpd of high-pressure hydrocarbon condensate to 770 bpd of stabilized (10 psia RVP) condensate.
Job 388
200 MMSCFD Cryogenic Gas Plant
200 MMSCFD Cryogenic Gas Plant designed for rich Delaware Basin shale gas (6.0 gal/mscf), 90% ethane recovery, 99+% propane recovery, and includes: Product pumps (1,300 psig discharge pressure), and 30,000 gallon product surge tank, modular MCC building, with 480 volt MCC and 4,160 volt soft starts for three 1,250 HP motors 4,500 HP refrigeration system, I/A system, ethane rejection and recovery capability.
Job 417
200 MMSCFD Cryogenic Gas Plant
200 MMSCFD Cryogenic Gas Plant designed for rich Delaware Basin shale gas (7.0 gal/f), 90% ethane recovery, 99+% propane recovery, and includes: Product pumps (1,300 psig discharge pressure), and 30,000 gallon product surge tank Modular MCC building, with 480 volt MCC and 4,160 volt soft starts for three 1,250 HP motors 4,500 HP refrigeration system, I/A system, ethane rejection and recovery capability. A high-pressure hydrocarbon condensate stabilization system is included along with an 800 GPM inlet amine treater.
Job 420
200 MMSCFD Cryogenic Gas Plant
200 MMSCFD Cryogenic Gas Plant designed for rich Delaware Basin shale gas (7.0 gal/mscf), 90% ethane recovery, 99+% propane recovery, and includes: Product pumps (1,300 psig discharge pressure), and 30,000 gallon product surge tank Modular MCC building, with 480 volt MCC and 4,160 volt soft starts for three 1,250 HP motors, 4,500 HP refrigeration system, I/A system, ethane rejection and recovery capability.
Job 299
20 MMSCFD Cryogenic Gas Plant For Counterpoint Energy
Redesigned and refurbished 20 MMSCFD cryogenic plant for CenterPoint Energy. Haughton, Louisiana.
Jasper has successfully completed and fully executed a LSTK EPC project in the Delaware basin for a repeat client. This is the third train Jasper has completed at this location. This Client chose Jasper’s Standard 200MMSCFD GSP cryogenic gas plant from our inventory, Jasper Amine Contactor and pre-treatment system, Jasper 42 GPM TEG Contactor and Regen System, interconnecting piping, flare, utilities, instrumentation, electrical, MCC, foundations, and a fully automated Allen Bradley control system with Wonderware front end.
Job 322
25 MMSCFD Refrigeration Plant with Stabilizer
Designed and fabricated 25 MMSCFD refrigeration plant with stabilizer. Pampa, Texas.
Job 326
100 MM/D Cryogenic Gas Plant
100 MM/D Cryo Plant, West Johnson Co Gas Plant, West Johnson County, TX, Phase 2
Job 328, Turnkey
80 MM/D Cryogenic Gas Plant
80 MM/D Cryo Plant, Crossroads Gas Plant, Harrison County, TX, Turnkey installed.
35 MM/D Cryo Plant, Cobb Gas Plant, Clendinin, WV, Ex-Works
Job 340
120 MM/D Cryogenic Gas Plant
120 MM/D Cryo Plant with Depropanizer, Houston 2 Gas Plant, Houston, PA, Ex-works.
Job 342
500 HP Refrigeration Addition
500 HP Refrigeration Addition, Arapaho 2 & NGL Booster Pump Addition, Arapaho 1, Butler, OK.
Job 345
60 MMSCFD Refrigeration Addition
Designed and fabricated 60 MMSCFD refrigeration addition to increase recovery. Butler, Oklahoma.
Job 347
250 GPM Amine Treating Plant
Designed and fabricated 250 gpm amine treating plant. Shreveport, Louisiana.
Job 443
200 MMSCFD Cryogenic Gas Plant
Jasper has successfully completed and fully executed a LSTK EPC project in the Delaware basin for a repeat client. This is the second train Jasper has completed at this location. The client chose Jasper’s standard 200 MMSCFD Cryogenic Plant, along with a 500 GPM Amine Inlet Treater and 4000 BPD Two Tower Stabilizer, interconnecting piping, flare, utilities, instrumentation, electrical, MCC, foundations, and a fully automated Allen Bradley ControlLogix control system with Wonderware front end.
Job 445
200 MMSCFD Cryogenic Gas Plant
Jasper has successfully completed and fully executed a LSTK EPC project in the Delaware basin for a repeat client. This is the second train Jasper has completed at this location. This project consisted of a Jasper 200MMSCFD GSP cryogenic gas plant, Jasper 200 GPM MDEA NGL Treater, 4500bbl harp style slug catchers, interconnecting piping, flare, utilities, instrumentation, electrical, MCC, foundations, fully automated DELTA V control system with SIS.
Job 408
200 MMSCFD Cryogenic Gas Plant
200 MMSCFD Cryogenic Gas Plant designed for rich Delaware Basin shale gas (6.0 gal/mscf), 90% ethane recovery, 99+% propane recovery, and includes: Product pumps (1,300 psig discharge pressure), and 30,000 gallon product surge tank, modular MCC building, with 480 volt MCC and 4,160 volt soft starts for three 1,250 HP motors 4,500 HP refrigeration system, I/A system, ethane rejection and recovery capability.